|
||
|
||
True costs of Amazon dam revealed The
proposed Belo Monte Dam along the Glenn Switkes THE
true costs of the Belo Monte Hydroelectric Project, planned for the
The panel found that the dam would have serious consequences for the region, its inhabitants, and ecosystems of the Amazon rainforest. In addition, its potential for contributing to climate change through greenhouse gas emissions is high. The panel - comprised of scientists from major Brazilian research institutions - reviewed the project's environmental impact assessment (EIA) and delivered a 230-page report to Ibama, the Brazilian government's environmental agency, on 1 October. In
early November, a judge in Cutting off the flow One
of the most alarming impacts identified by the specialists is that Belo
Monte Dam would require diverting more than 80% of the flow of the The experts also found that the number of people who would be directly affected by the dam is likely far greater than the 19,000 indicated in official studies. More than 40,000 people could be affected. Belo Monte Dam would be the world's third largest dam project in 'installed capacity' if not in actual energy production. Despite having an installed generating capacity of 11,231 MW, it would generate as little as 1,000 MW during the three- to four-month low-water season. Francisco Hernandez, electrical engineer and co-coordinator of the panel, said: 'The expert panel's report highlights the folly of Belo Monte. The project could cost up to $19 billion, making it an extremely inefficient investment given that the dam will generate only a fraction of its installed capacity during the dry season. And this doesn't even take into account the enormous social costs and environmental devastation that the project would cause. No one knows the true costs of Belo Monte.' The
issue of greenhouse gas emissions from a mega-dam in the Amazon rainforest
was also addressed by the panel. Philip Fearnside, Ecologist from the
National Institute for Amazon Research (INPA), said that although the
EIA affirms that hydroelectric dams have lower emissions than thermoelectric
plants of the same capacity, studies in Research commissioned by International Rivers in 2005 revealed major greenhouse gas emissions from an earlier design of the dam complex, which included a large upstream reservoir to make Belo Monte economically viable during the dry season. The government now says it no longer plans to build the upstream dam, which places Belo Monte's economic viability in doubt. If the project includes the expected series of large dams and dikes needed to make it economically viable, it would require 'moving a volume of earth and rocks on the scale of that excavated for the building of the Panama Canal,' the panel states. The $9 billion project is the largest in the Brazilian government's Growth Acceleration Programme, which focuses on large-scale infrastructure projects, yet there has been little public debate regarding its impacts. The government seems uninterested in debate on this flagship project - one of 120 new large dams proposed for the Amazon. Brazilian
Indians from 14 ethnic groups are threatening violence if the government
goes ahead with the dam, which would be In
October, This article is reproduced from World Rivers Review (December 2009), which is published by the non-governmental organisation International Rivers. Glenn Switkes, who was International Rivers' Amazon programme director, passed away not long after writing this. He is remembered by his colleagues as 'a river warrior of unbreakable passion, a much-loved inspiration and teacher to river defenders, and an effective thorn in the side of river-wrecking politicians and bureaucrats.' *Third World Resurgence No. 234, February 2010, pp 13-14 |
||
|